Drying and mixing equipment in the use of reducer Note
Sources: | Release date:
2009-07-29
| Browse volume:
Key word:
1, the use of reducer according to the carrying capacity table to select the power to match the power equipment to match, the transmission method can be determined according to need.
2, the reducer should be cleaned before use, and according to the provisions of the amount of oil filling HJ-40 or HJ-50 mechanical oil, the use of the process should pay attention to observe the oil scale, the amount of oil shall not exceed or below the oil scale On the highest or lowest mark. Also note that the vent plug on the reducer cover can not be blocked by dust or other debris to prevent the possibility of increasing the oil spill in the reducer cavity due to increased oil pressure.
3, the reducer is the intermediate transmission mechanism. The active gear shaft is driven by the power equipment, and the low speed shaft drives the power to drive the working machine. So the installation should ensure that the three positions are correct. When using the coupling drive, should ensure that the axis of the different axis of not more than 0.075 mm, the axis of the skew is not greater than 30 degrees, the use of other means of transmission, should ensure that the correct installation location.
4, after the installation of reducer, should be carried no-load operation, check the various parts of the normal operation, before the load work. In the case of full load, the temperature rise of the gear unit should not exceed 40 degrees Celsius, but the maximum oil temperature should be less than 60 degrees Celsius. If you find the temperature rise is too high or the sound is not normal, should stop the analysis of the reasons, troubleshooting can continue to use.
5, the reducer in the use of the process, every half a month to check, open the hole cover, check the gear tooth surface contact marks and the situation. In six months should be a comprehensive inspection once, open the cover, a comprehensive inspection of the tooth surface and bearing wear, such as the problem, should take measures to clear the trap.
6, the reducer seal; reducer split surface, embedded end cover Zhou Yuan as the hole cover should be coated with sealant to prevent leakage.
2, the reducer should be cleaned before use, and according to the provisions of the amount of oil filling HJ-40 or HJ-50 mechanical oil, the use of the process should pay attention to observe the oil scale, the amount of oil shall not exceed or below the oil scale On the highest or lowest mark. Also note that the vent plug on the reducer cover can not be blocked by dust or other debris to prevent the possibility of increasing the oil spill in the reducer cavity due to increased oil pressure.
3, the reducer is the intermediate transmission mechanism. The active gear shaft is driven by the power equipment, and the low speed shaft drives the power to drive the working machine. So the installation should ensure that the three positions are correct. When using the coupling drive, should ensure that the axis of the different axis of not more than 0.075 mm, the axis of the skew is not greater than 30 degrees, the use of other means of transmission, should ensure that the correct installation location.
4, after the installation of reducer, should be carried no-load operation, check the various parts of the normal operation, before the load work. In the case of full load, the temperature rise of the gear unit should not exceed 40 degrees Celsius, but the maximum oil temperature should be less than 60 degrees Celsius. If you find the temperature rise is too high or the sound is not normal, should stop the analysis of the reasons, troubleshooting can continue to use.
5, the reducer in the use of the process, every half a month to check, open the hole cover, check the gear tooth surface contact marks and the situation. In six months should be a comprehensive inspection once, open the cover, a comprehensive inspection of the tooth surface and bearing wear, such as the problem, should take measures to clear the trap.
6, the reducer seal; reducer split surface, embedded end cover Zhou Yuan as the hole cover should be coated with sealant to prevent leakage.
Related articles
- 2017-04-10 > Mixing Boiling Dryer Installation Location and Environmental Requirements
- 2017-04-03 > The working principle of box boiling dryer
- 2017-03-22 > Structure and Working Flow of Box - type Boiling Dryer
- 2017-03-15 > Characteristics of three - dimensional motion mixer
- 2017-03-06 > Several Technical Characteristics of Medicinal
- 2017-02-27 > The core components of the three - dimensional motion mixer
- 2017-02-25 > Detailed description of the medicinal GMP oven
- 2017-02-19 > Operation Experience Sharing of Rotary Double Cone Vacuum Dryer
Related products